Sports Minister Gary Hunt has confirmed that the long-delayed Taruba stadium and sporting complex has already cost the government of Trinidad and Tobago TT$700 million. And he told the House of Representatives he cannot give a final cost of the project or when it would be completed.
Hunt was responding Friday to a question by Caroni Central MP Dr Hamza Rafeeq, who wanted to know. Rafeeq was asking for details on:
- The projected cost of the entire project
- The amount of money already spent on it
- The expected completion date
- The projected annual cost of maintenance of the complex after completion of construction
He gave a breakdown on costs so far of the project, which is being managed by the Urban Development Corporation of T&T (UDeCOTT):
- Site works, drainage, roads and utilities—$108,697,537
- Stadium structure—$419,536,998
- Project design, project management, construction management, consultants, Osha, security and site office—$103,687,327